🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Idaho

ONSHORE WIND · WEST

Onshore wind project 763, Power County

Onshore wind project 763, Power County is a 300 MW onshore wind request in interconnection study in the West interconnection queue, in Power County, Idaho, connecting to Idaho Power Company.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
763
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Connection point (POI)
Populus-Borah 345kV #1 line
Location
Power County, Idaho
Technology
Wind: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
Cluster Study
Queue status
Active
Entered queue
27 March 2025
Proposed online date
May 2030

Location

Marker shows the centre of Power County; the queue data does not give exact sites.

Power plants in Idaho · Transmission lines in Idaho

Other requests in Power County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem