United States › Grid › Interconnection queues › Minnesota

SOLAR · MISO

Solar project J3884, Benton County

Solar project J3884, Benton County is a 300 MW solar request in interconnection study in the MISO interconnection queue, in Benton County, Minnesota.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3884
Grid region
MISO (Midcontinent)
Connection point (POI)
BENTON COUNTY 345 - START DBL CKT W/EW LINE 345.0kV
Location
Benton County, Minnesota
Technology
Solar: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
9 February 2025
Proposed online date
September 2030

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem