BATTERY STORAGE · MISO

Surplus; J1426

Surplus; J1426 is a 100 MW battery storage request in interconnection study in the MISO interconnection queue, in Benton County, Minnesota, connecting to GREAT RIVER ENERGY.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1088
Grid region
MISO (Midcontinent)
Utility / transmission owner
GREAT RIVER ENERGY
Connection point (POI)
GRE-BENTON 7 115kV
Location
Benton County, Minnesota
Technology
Battery: 100 MW
Total requested
100 MW
Queue status
Active
Entered queue
17 March 2025
Proposed online date
June 2027

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Benton County