BATTERY STORAGE · WESTBattery storage project T2-075, San Juan County
Battery storage project T2-075, San Juan County is a 300 MW battery storage request in interconnection study in the West interconnection queue, in San Juan County, Utah, connecting to PacifiCorp.
Queue statusIn planning
- PlanningQueued Sep 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- T2-075
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Pinto substation
- Location
- San Juan County, Utah
- Technology
- Battery: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 12 September 2025
- Proposed online date
- December 2027
Location
Marker shows the centre of San Juan County; the queue data does not give exact sites.
Other requests in San Juan County
- Solar + storage project T2-071, San Juan CountySolar + storage · 199 MW · in study
- Onshore wind project 384, San Juan CountyOnshore wind · 60.0 MW · built
- Gas project C4-083, San Juan CountyGas · 525 MW · withdrawn
- Onshore wind project C4-020, San Juan CountyOnshore wind · 402 MW · withdrawn
- Battery storage project C3-167, San Juan CountyBattery storage · 300 MW · withdrawn
- Solar project 1202, San Juan CountySolar · 300 MW · withdrawn
- Solar + storage project 1224, San Juan CountySolar + storage · 250 MW · withdrawn
- Solar project 819, San Juan CountySolar · 240 MW · withdrawn
- Solar + storage project C1-06, San Juan CountySolar + storage · 200 MW · withdrawn
- Solar + storage project C3-164, San Juan CountySolar + storage · 200 MW · withdrawn
- Solar + storage project C1-07, San Juan CountySolar + storage · 200 MW · withdrawn
- Solar + storage project C2-148, San Juan CountySolar + storage · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem