Solar + storage project C2-148, San Juan County

Solar + storage project C2-148, San Juan County is a 200 MW solar + storage request withdrawn in the West interconnection queue, in San Juan County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C2-148
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Pinto substation
Location
San Juan County, Utah
Technology
Solar: 200 MW Β· Battery
Total requested
200 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
15 May 2022
Proposed online date
May 2025

Location

Marker shows the centre of San Juan County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in San Juan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem