Solar project 819, San Juan County

Solar project 819, San Juan County is a 240 MW solar request withdrawn in the West interconnection queue, in San Juan County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
819
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
PacifiCorp
Connection point (POI)
Pinto substation
Location
San Juan County, Utah
Technology
Solar: 240 MW
Total requested
240 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
11 November 2016
Proposed online date
December 2019

Location

Marker shows the centre of San Juan County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in San Juan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem