🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in SPP (Southwest Power Pool) — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown692152.4 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

692 requests · page 9 of 14
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2019-039, Butler County
Solar
175 MWAgreement signed Butler, NESPP May 2019target 2027
Solar project GEN-2024-040, Nemaha County
Solar
174 MWIn study Nemaha, NESPP Oct 2024target 2029
Battery storage project ERAS-2025-029, Wyandotte County
Battery storage
170 MWIn study Wyandotte, KSSPP Oct 2025target 2027
Battery storage project GEN-2023-SR4, Burke County
Battery storage
170 MWAgreement signed Burke, NDSPP Dec 2022target 2026
Battery storage project GEN-2024-051, Lancaster County
Battery storage
170 MWIn study Lancaster, NESPP Oct 2024target 2028
Solar + storage project GEN-2024-161, Jackson County
Solar + storage
170 MWIn study Jackson, OKSPP Mar 2025target 2030
Battery storage project GEN-2025-SR31, Madison County
Battery storage
170 MWIn study Madison, NESPP Nov 2025target 2026
Solar project GEN-2024-297, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Solar project GEN-2024-296, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Battery storage project GEN-2024-084, Lawrence County
Battery storage
167 MWIn study Lawrence, MOSPP Oct 2024target 2028
Solar project GEN-2024-298, Mcintosh County
Solar
167 MWIn study Mcintosh, OKSPP Mar 2025target 2030
Onshore wind project GEN-2011-020, Ellis County
Onshore wind
166 MWAgreement signed Ellis, OKSPP Mar 2011target 2027
Solar project GEN-2018-106, Caddo Parish County
Solar
165 MWAgreement signed Caddo Parish, LASPP Nov 2018target 2028
Solar project GEN-2024-085, Rush County
Solar
160 MWIn study Rush, KSSPP Oct 2024target 2029
Battery storage project GEN-2024-324, Chaves County
Battery storage
160 MWIn study Chaves, NMSPP Mar 2025target 2028
Solar project GEN-2017-140, Wagoner County
Solar
160 MWAgreement signed Wagoner, OKSPP Nov 2017target 2027
Solar + storage project GEN-2024-219, Murray County
Solar + storage
160 MWIn study Murray, OKSPP Mar 2025target 2030
Solar + storage project GEN-2024-360, Seminole County
Solar + storage
160 MWIn study Seminole, OKSPP Mar 2025target 2029
Solar + storage project GEN-2024-122, Marion County
Solar + storage
160 MWIn study Marion, TXSPP Mar 2025target 2029
Solar project GEN-2024-072, Mitchell County
Solar
160 MWIn study Mitchell, KSSPP Oct 2024target 2029
Gas project ERAS-2025-014, Lea County
Gas
160 MWIn study Lea, NMSPP Oct 2025target 2029
Solar project GEN-2021-101, Douglas County
Solar
159 MWAgreement signed Douglas, KSSPP May 2021target 2027
Solar + storage project GEN-2024-265, Lea County
Solar + storage
155 MWIn study Lea, NMSPP Mar 2025target 2029
Solar project GEN-2019-045, Woods County
Solar
155 MWAgreement signed Woods, OKSPP May 2019target 2028
Solar + storage project GEN-2024-205, Stafford County
Solar + storage
155 MWIn study Stafford, KSSPP Mar 2025target 2029
Solar + storage project GEN-2021-063, Mccurtain County
Solar + storage
155 MWIn study Mccurtain, OKSPP Apr 2021target 2027
Battery storage project GEN-2017-221, Sedgwick County
Battery storage
152 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2026
Solar project GEN-2017-011, Ellis County
Solar
152 MWAgreement signed Ellis, OKSPP May 2017target 2026
Onshore wind project GEN-2017-146, Castro County
Onshore wind
152 MWAgreement signed Castro, TXSPP Nov 2017target 2026
Battery storage project GEN-2018-072, Kay County
Battery storage
151 MWAgreement signed Kay, OKSPP Oct 2018target 2027
Battery storage project GEN-2018-071, Kay County
Battery storage
151 MWAgreement signed Kay, OKSPP Oct 2018target 2027
Solar + storage project GEN-2024-261, Lea County
Solar + storage
150 MWIn study Lea, NMSPP Mar 2025target 2029
Solar project GEN-2018-003, Bowie County
Solar
150 MWAgreement signed Bowie, TXSPP Apr 2018target 2027
Battery storage project GEN-2024-065, Dodge County
Battery storage
150 MWIn study Dodge, NESPP Oct 2024target 2029
Onshore wind project GEN-2017-086, Harper County
Onshore wind
150 MWAgreement signed Harper, KSSPP May 20172025
Solar + storage project GEN-2022-111, Marion County
Solar + storage
150 MWIn study Marion, TXSPP Feb 2023target 2027
Battery storage project GEN-2024-325, Chaves County
Battery storage
150 MWIn study Chaves, NMSPP Mar 2025target 2028
Solar project GEN-2019-003, Roosevelt County
Solar
150 MWAgreement signed Roosevelt, NMSPP Apr 2019target 2027
Battery storage project GEN-2022-235, Canadian County
Battery storage
150 MWIn study Canadian, OKSPP Feb 2023target 2028
Solar project GEN-2020-088, Jasper County
Solar
150 MWAgreement signed Jasper, MOSPP Apr 2020target 2028
Battery storage project GEN-2024-244, Texas County
Battery storage
150 MWIn study Texas, OKSPP Mar 2025target 2029
Solar project GEN-2023-GR5, Lamb County
Solar
150 MWAgreement signed Lamb, TXSPP Jul 2023target 2026
Battery storage project GEN-2023-170, Chariton County
Battery storage
150 MWIn study Chariton, MOSPP Oct 2023target 2028
Solar project GEN-2023-SR28, Ford County
Solar
150 MWAgreement signed Ford, KSSPP Oct 20232025
Battery storage project GEN-2024-276, Shawnee County
Battery storage
150 MWIn study Shawnee, KSSPP Mar 2025target 2030
Battery storage project GEN-2023-057, Pawnee County
Battery storage
150 MWIn study Pawnee, OKSPP Oct 2023target 2028
Solar project GEN-2024-210, Cheyenne County
Solar
150 MWIn study Cheyenne, KSSPP Mar 2025target 2028
Battery storage project GEN-2023-171, Jackson County
Battery storage
150 MWIn study Jackson, MOSPP Oct 2023target 2028
Solar project GEN-2019-055, Edwards County
Solar
150 MWAgreement signed Edwards, KSSPP May 2019target 2028
Battery storage project GEN-2024-306, Lea County
Battery storage
150 MWIn study Lea, NMSPP Mar 2025target 2031
Page 9 of 14

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)