Solar project GEN-2019-039, Butler County Solar |
175 MW | Agreement signed |
Butler, NE | SPP |
May 2019 | target 2027 |
Solar project GEN-2024-040, Nemaha County Solar |
174 MW | In study |
Nemaha, NE | SPP |
Oct 2024 | target 2029 |
Battery storage project ERAS-2025-029, Wyandotte County Battery storage |
170 MW | In study |
Wyandotte, KS | SPP |
Oct 2025 | target 2027 |
Battery storage project GEN-2023-SR4, Burke County Battery storage |
170 MW | Agreement signed |
Burke, ND | SPP |
Dec 2022 | target 2026 |
Battery storage project GEN-2024-051, Lancaster County Battery storage |
170 MW | In study |
Lancaster, NE | SPP |
Oct 2024 | target 2028 |
Solar + storage project GEN-2024-161, Jackson County Solar + storage |
170 MW | In study |
Jackson, OK | SPP |
Mar 2025 | target 2030 |
Battery storage project GEN-2025-SR31, Madison County Battery storage |
170 MW | In study |
Madison, NE | SPP |
Nov 2025 | target 2026 |
Solar project GEN-2024-297, Mcintosh County Solar |
167 MW | In study |
Mcintosh, OK | SPP |
Mar 2025 | target 2030 |
Solar project GEN-2024-296, Mcintosh County Solar |
167 MW | In study |
Mcintosh, OK | SPP |
Mar 2025 | target 2030 |
Battery storage project GEN-2024-084, Lawrence County Battery storage |
167 MW | In study |
Lawrence, MO | SPP |
Oct 2024 | target 2028 |
Solar project GEN-2024-298, Mcintosh County Solar |
167 MW | In study |
Mcintosh, OK | SPP |
Mar 2025 | target 2030 |
Onshore wind project GEN-2011-020, Ellis County Onshore wind |
166 MW | Agreement signed |
Ellis, OK | SPP |
Mar 2011 | target 2027 |
Solar project GEN-2018-106, Caddo Parish County Solar |
165 MW | Agreement signed |
Caddo Parish, LA | SPP |
Nov 2018 | target 2028 |
Solar project GEN-2024-085, Rush County Solar |
160 MW | In study |
Rush, KS | SPP |
Oct 2024 | target 2029 |
Battery storage project GEN-2024-324, Chaves County Battery storage |
160 MW | In study |
Chaves, NM | SPP |
Mar 2025 | target 2028 |
Solar project GEN-2017-140, Wagoner County Solar |
160 MW | Agreement signed |
Wagoner, OK | SPP |
Nov 2017 | target 2027 |
Solar + storage project GEN-2024-219, Murray County Solar + storage |
160 MW | In study |
Murray, OK | SPP |
Mar 2025 | target 2030 |
Solar + storage project GEN-2024-360, Seminole County Solar + storage |
160 MW | In study |
Seminole, OK | SPP |
Mar 2025 | target 2029 |
Solar + storage project GEN-2024-122, Marion County Solar + storage |
160 MW | In study |
Marion, TX | SPP |
Mar 2025 | target 2029 |
Solar project GEN-2024-072, Mitchell County Solar |
160 MW | In study |
Mitchell, KS | SPP |
Oct 2024 | target 2029 |
Gas project ERAS-2025-014, Lea County Gas |
160 MW | In study |
Lea, NM | SPP |
Oct 2025 | target 2029 |
Solar project GEN-2021-101, Douglas County Solar |
159 MW | Agreement signed |
Douglas, KS | SPP |
May 2021 | target 2027 |
Solar + storage project GEN-2024-265, Lea County Solar + storage |
155 MW | In study |
Lea, NM | SPP |
Mar 2025 | target 2029 |
Solar project GEN-2019-045, Woods County Solar |
155 MW | Agreement signed |
Woods, OK | SPP |
May 2019 | target 2028 |
Solar + storage project GEN-2024-205, Stafford County Solar + storage |
155 MW | In study |
Stafford, KS | SPP |
Mar 2025 | target 2029 |
Solar + storage project GEN-2021-063, Mccurtain County Solar + storage |
155 MW | In study |
Mccurtain, OK | SPP |
Apr 2021 | target 2027 |
Battery storage project GEN-2017-221, Sedgwick County Battery storage |
152 MW | Agreement signed |
Sedgwick, KS | SPP |
Nov 2017 | target 2026 |
Solar project GEN-2017-011, Ellis County Solar |
152 MW | Agreement signed |
Ellis, OK | SPP |
May 2017 | target 2026 |
Onshore wind project GEN-2017-146, Castro County Onshore wind |
152 MW | Agreement signed |
Castro, TX | SPP |
Nov 2017 | target 2026 |
Battery storage project GEN-2018-072, Kay County Battery storage |
151 MW | Agreement signed |
Kay, OK | SPP |
Oct 2018 | target 2027 |
Battery storage project GEN-2018-071, Kay County Battery storage |
151 MW | Agreement signed |
Kay, OK | SPP |
Oct 2018 | target 2027 |
Solar + storage project GEN-2024-261, Lea County Solar + storage |
150 MW | In study |
Lea, NM | SPP |
Mar 2025 | target 2029 |
Solar project GEN-2018-003, Bowie County Solar |
150 MW | Agreement signed |
Bowie, TX | SPP |
Apr 2018 | target 2027 |
Battery storage project GEN-2024-065, Dodge County Battery storage |
150 MW | In study |
Dodge, NE | SPP |
Oct 2024 | target 2029 |
Onshore wind project GEN-2017-086, Harper County Onshore wind |
150 MW | Agreement signed |
Harper, KS | SPP |
May 2017 | 2025 |
Solar + storage project GEN-2022-111, Marion County Solar + storage |
150 MW | In study |
Marion, TX | SPP |
Feb 2023 | target 2027 |
Battery storage project GEN-2024-325, Chaves County Battery storage |
150 MW | In study |
Chaves, NM | SPP |
Mar 2025 | target 2028 |
Solar project GEN-2019-003, Roosevelt County Solar |
150 MW | Agreement signed |
Roosevelt, NM | SPP |
Apr 2019 | target 2027 |
Battery storage project GEN-2022-235, Canadian County Battery storage |
150 MW | In study |
Canadian, OK | SPP |
Feb 2023 | target 2028 |
Solar project GEN-2020-088, Jasper County Solar |
150 MW | Agreement signed |
Jasper, MO | SPP |
Apr 2020 | target 2028 |
Battery storage project GEN-2024-244, Texas County Battery storage |
150 MW | In study |
Texas, OK | SPP |
Mar 2025 | target 2029 |
Solar project GEN-2023-GR5, Lamb County Solar |
150 MW | Agreement signed |
Lamb, TX | SPP |
Jul 2023 | target 2026 |
Battery storage project GEN-2023-170, Chariton County Battery storage |
150 MW | In study |
Chariton, MO | SPP |
Oct 2023 | target 2028 |
Solar project GEN-2023-SR28, Ford County Solar |
150 MW | Agreement signed |
Ford, KS | SPP |
Oct 2023 | 2025 |
Battery storage project GEN-2024-276, Shawnee County Battery storage |
150 MW | In study |
Shawnee, KS | SPP |
Mar 2025 | target 2030 |
Battery storage project GEN-2023-057, Pawnee County Battery storage |
150 MW | In study |
Pawnee, OK | SPP |
Oct 2023 | target 2028 |
Solar project GEN-2024-210, Cheyenne County Solar |
150 MW | In study |
Cheyenne, KS | SPP |
Mar 2025 | target 2028 |
Battery storage project GEN-2023-171, Jackson County Battery storage |
150 MW | In study |
Jackson, MO | SPP |
Oct 2023 | target 2028 |
Solar project GEN-2019-055, Edwards County Solar |
150 MW | Agreement signed |
Edwards, KS | SPP |
May 2019 | target 2028 |
Battery storage project GEN-2024-306, Lea County Battery storage |
150 MW | In study |
Lea, NM | SPP |
Mar 2025 | target 2031 |