United States › Grid › Interconnection queues › Kansas

SOLAR · SPP

Solar project GEN-2021-101, Douglas County

Solar project GEN-2021-101, Douglas County is a 159 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Douglas County, Kansas, connecting to WERE.

Queue statusConsented
  1. PlanningQueued May 2021 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2021-101
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Evergy's Midland Substation 115kV bus
Location
Douglas County, Kansas
Technology
Solar: 159 MW
Total requested
159 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
25 May 2021
Proposed online date
September 2027

Location

Marker shows the centre of Douglas County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Douglas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem