United States βΊ Grid βΊ Interconnection queues βΊ Kansas
BATTERY STORAGE Β· SPPBattery storage project GEN-2023-190, Douglas County
Battery storage project GEN-2023-190, Douglas County is a 100 MW battery storage request withdrawn in the SPP interconnection queue, in Douglas County, Kansas, connecting to Evergy.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-190
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- Evergy
- Connection point (POI)
- Bismark JCT 35 115 kV
- Location
- Douglas County, Kansas
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- May 2028
- Withdrawn
- November 2023
Location
Marker shows the centre of Douglas County; the queue data does not give exact sites.
Other requests in Douglas County
- Solar project GEN-2021-101, Douglas CountySolar Β· 159 MW Β· agreement signed
- Hydro project GEN-2010-036, Douglas CountyHydro Β· 4.6 MW Β· built
- Onshore wind project GEN-2013-043, Douglas CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project GEN-2014-050, Douglas CountyOnshore wind Β· 100 MW Β· withdrawn
- Battery storage project GEN-2021-102, Douglas CountyBattery storage Β· 80.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem