United States › Grid › Interconnection queues › Kansas
SOLAR · SPPSolar project GEN-2024-072, Mitchell County
Solar project GEN-2024-072, Mitchell County is a 160 MW solar request in interconnection study in the SPP interconnection queue, in Mitchell County, Kansas, connecting to SUNC.
Queue statusIn planning
- PlanningQueued Oct 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-072
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SUNC
- Connection point (POI)
- Beloit 115 kV Substation
- Location
- Mitchell County, Kansas
- Technology
- Solar: 160 MW
- Total requested
- 160 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 30 October 2024
- Proposed online date
- April 2029
Location
Marker shows the centre of Mitchell County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem