Solar project GEN-2023-GR5, Lamb County

Solar project GEN-2023-GR5, Lamb County is a 150 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Lamb County, Texas, connecting to Xcel/SPS.

Queue statusConsented
  1. PlanningQueued Jul 2023 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2023-GR5
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
Xcel/SPS
Connection point (POI)
Plant X 115 kV Substation
Location
Lamb County, Texas
Technology
Solar: 150 MW
Total requested
150 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
18 July 2023
Proposed online date
April 2026

Location

Marker shows the centre of Lamb County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Lamb County