Solar project GEN-2017-080, Lamb County

Solar project GEN-2017-080, Lamb County is a 525 MW solar request withdrawn in the SPP interconnection queue, in Lamb County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedMay 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-080
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tolk 230 kV substation
Location
Lamb County, Texas
Technology
Solar: 525 MW
Total requested
525 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 May 2017
Proposed online date
December 2020
Withdrawn
May 2021

Location

Marker shows the centre of Lamb County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Lamb County