Solar project GEN-2024-210, Cheyenne County

Solar project GEN-2024-210, Cheyenne County is a 150 MW solar request in interconnection study in the SPP interconnection queue, in Cheyenne County, Kansas, connecting to SUNC.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-210
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
St. Francis Tap 115 kV Substation
Location
Cheyenne County, Kansas
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
June 2028

Location

Marker shows the centre of Cheyenne County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem