United States › Grid › Interconnection queues › North Dakota
BATTERY STORAGE · SPPBattery storage project GEN-2023-SR4, Burke County
Battery storage project GEN-2023-SR4, Burke County is a 170 MW battery storage request with a signed interconnection agreement in the SPP interconnection queue, in Burke County, North Dakota, connecting to BEPC.
Queue statusConsented
- PlanningQueued Dec 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2023-SR4
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- BEPC
- Connection point (POI)
- Tande 345 kV Substation
- Location
- Burke County, North Dakota
- Technology
- Battery: 170 MW
- Total requested
- 170 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 15 December 2022
- Proposed online date
- June 2026
Location
Marker shows the centre of Burke County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Burke County
- Gas project GI-1103, Burke CountyGas · 0.8 MW · agreement signed
- Onshore wind project GEN-2016-151, Burke CountyOnshore wind · 202 MW · built
- Gas project GI-1009, Burke CountyGas · 0.3 MW · built
- Battery storage project GEN-2022-SR1, Burke CountyBattery storage · 104 MW · withdrawn
- Onshore wind project GEN-2016-152, Burke CountyOnshore wind · 102 MW · withdrawn
- Gas project GI-1010, Burke CountyGas · 0.8 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem