United States › Grid › Interconnection queues › North Dakota
GAS · WESTGas project GI-1009, Burke County
Gas project GI-1009, Burke County is a 0.3 MW gas request built and operating in the West interconnection queue, in Burke County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.
Request details
- Queue ID
- GI-1009
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- WAPA/BEPC/HCPD Integrated System
- Developer
- Blaise Energy
- Connection point (POI)
- Kenmare 115kV
- Location
- Burke County, North Dakota
- Technology
- Gas: 0.3 MW
- Total requested
- 0.3 MW
- Service type
- Energy only (ERIS)
- Study phase
- IAE/IS
- Queue status
- Operational
- Entered queue
- 27 September 2010
- Proposed online date
- March 2011
Location
Marker shows the centre of Burke County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Burke County
- Battery storage project GEN-2023-SR4, Burke CountyBattery storage · 170 MW · agreement signed
- Gas project GI-1103, Burke CountyGas · 0.8 MW · agreement signed
- Onshore wind project GEN-2016-151, Burke CountyOnshore wind · 202 MW · built
- Battery storage project GEN-2022-SR1, Burke CountyBattery storage · 104 MW · withdrawn
- Onshore wind project GEN-2016-152, Burke CountyOnshore wind · 102 MW · withdrawn
- Gas project GI-1010, Burke CountyGas · 0.8 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem