United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· SPP

Onshore wind project GEN-2016-152, Burke County

Onshore wind project GEN-2016-152, Burke County is a 102 MW onshore wind request withdrawn in the SPP interconnection queue, in Burke County, North Dakota, connecting to WAPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedJan 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2016-152
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Tande 345kV
Location
Burke County, North Dakota
Technology
Wind: 102 MW
Total requested
102 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 November 2016
Proposed online date
December 2019
Withdrawn
January 2019

Location

Marker shows the centre of Burke County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Burke County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem