BATTERY STORAGE · SPP

Battery storage project GEN-2023-171, Jackson County

Battery storage project GEN-2023-171, Jackson County is a 150 MW battery storage request in interconnection study in the SPP interconnection queue, in Jackson County, Missouri, connecting to INDN.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2023-171
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
INDN
Connection point (POI)
Sub M 161 kV Substation
Location
Jackson County, Missouri
Technology
Battery: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
2 October 2023
Proposed online date
June 2028

Location

Marker shows the centre of Jackson County; the queue data does not give exact sites.