Completed queue projects in ERCOT (Texas) — page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown61395.3 GW
Active in queue447.3 GW1,986 requests
Agreement signed119.3 GW578 requests
Withdrawn1,158262.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

613 requests · page 7 of 13
ProjectCapacityStatusLocationRegionQueuedOnline
East Blackland Solar
Solar + storage · East Blackland Holdings LLC
144 MWOperating Travis, TXERCOT Apr 20152021
Tavener Solar
Solar · Fort Bend Solar LLC
144 MWOperating Fort Bend, TXERCOT Dec 20162023
Sheep Creek Storage
Other · Longhorn Storage LLC
142 MWOperating Callahan, TXERCOT Jul 20212024
Pioneer DJ Wind
Onshore wind · Pioneer Hutt Wind Energy LLC
140 MWOperating Midland, TXERCOT Oct 20212025
Louis (Buffalo Gap 3)
Onshore wind · AES Seawest
138 MWOperating ERCOT Mar 2006target 2006
Nebula Solar
Solar · Rayos Del Sol Solar Project, LLC
138 MWOperating Cameron, TXERCOT Mar 20172022
Strategic Solar 1
Solar · Elm Branch Solar 1, LLC
137 MWOperating Ellis, TXERCOT Apr 20182022
Sweetwater Wind 3
Onshore wind · Sweetwater Wind 3 LLC
136 MWOperating ERCOT Sep 2005target 2005
Blue Summit I Repower
Wind + storage
135 MWOperating Wilbarger, TXERCOT Oct 20212024
Blue Summit Windfarm
Onshore wind · NextEra Energy
135 MWOperating ERCOT Mar 20112013
Elara Solar
Solar · Elara Energy Project, LLC
132 MWOperating Frio, TXERCOT Mar 20192022
Giga Texas Energy Storage
Other · Giga Texas Energy, LLC.
131 MWOperating Travis, TXERCOT Apr 20212024
Orange Grove Solar
Solar + storage · Enbridge Solar (Orange Grove), LLC
131 MWOperating Jim Wells, TXERCOT Jul 20192025
Lamar Power Upgrade
Gas · Nextera
130 MWOperating ERCOT Jul 20132016
Scurry County Wind Farm
Onshore wind · Wind Tex Energy
130 MWOperating ERCOT Jul 2005target 2007
Vision Solar 1
Solar · Briar Creek Solar 1, LLC
129 MWOperating Navarro, TXERCOT Apr 20182022
Fegc
Gas · Friendswood Energy Genco
129 MWOperating ERCOT Feb 20122018
Anchor Wind II
Onshore wind
129 MWOperating Eastland, TXERCOT Apr 20212024
Roadrunner Crossing Wind SLF
Wind + storage · Roadrunner Crossing Wind Farm, LLC
128 MWOperating Eastland, TXERCOT Sep 20172024
Roadrunner Crossing Wind II SLF
Onshore wind · Roadrunner Crossing Wind Farm, LLC
127 MWOperating Eastland, TXERCOT Jul 20202024
Airtricity Champion Wind Farm
Onshore wind · Airtricity, INC
126 MWOperating ERCOT Dec 2006target 2010
Coniglio Solar
Solar · BT Coniglio Solar, LLC
126 MWOperating Fannin, TXERCOT Nov 20172021
Tyler Bluff Wind
Onshore wind · Southern Power Company
126 MWOperating ERCOT Jul 20142017
Connolly Storage
Other · BT Connolly Storage, LLC
125 MWOperating Wise, TXERCOT Oct 20212024
Wigeon Whistle BESS
Other · Wigeon Whistle BESS
123 MWOperating Collin, TXERCOT Apr 20222024
Vortex BESS
Other · AZURE SKY WIND STORAGE LLC
122 MWOperating Throckmorton, TXERCOT Dec 20192023
Black Springs BESS
Battery storage · Black Springs BESS LLC
121 MWOperating Palo Pinto, TXERCOT Apr 20222025
East Pecos Solar
Solar · First Solar
120 MWOperating ERCOT Nov 20142017
Stanton Wind Energy
Onshore wind · Wind Tex Energy LLC
120 MWOperating ERCOT Nov 2005target 2008
Barton Chapel Wind Farm
Onshore wind · Gamesa Energia Southwest
120 MWOperating ERCOT Dec 2004target 2007
Wagyu Solar
Solar · Cypress Creek Renewables
120 MWOperating Brazoria, TXERCOT Feb 20172021
Camp Springs Wind Farm II
Onshore wind · Invenergy LLC
120 MWOperating ERCOT Jun 2006target 2007
Gunsight Mt W
Onshore wind · Invenergy
120 MWOperating ERCOT Jul 20062016
Buffalo Gap1
Onshore wind · SeaWest WindPower
120 MWOperating ERCOT Jun 2003target 2006
Maverick Creek II Wind
Onshore wind · Maverick Creek Wind, LLC
119 MWOperating Concho, TXERCOT Jan 20182022
Elbow Creek Wind Project
Onshore wind · Elbow Creek Wind Project LLC
117 MWOperating ERCOT Apr 2007target 2008
BlueBell Solar II
Solar · Bluebell Solar
115 MWOperating Sterling, TXERCOT Oct 20182021
Airtricity Panther Creek 2
Onshore wind · Airtricity, Inc.
115 MWOperating ERCOT Nov 2006target 2008
Galloway 2 Solar
Solar · 224WB 8me LLC
114 MWOperating Concho, TXERCOT Aug 20192024
Wolf Ridge Windfarm
Onshore wind · FPL Energy, LLC
113 MWOperating ERCOT Mar 2006target 2008
Limestone Electric Gen Station upgrade
Coal · Texas Genco
110 MWOperating ERCOT Jul 2004target 1985
Los Vientos V
Onshore wind · Duke Energy
110 MWOperating ERCOT Jul 20122016
West Texas Solar
Solar · OCI Solar
110 MWOperating ERCOT Dec 20132017
Emerald Grove Solar
Solar · Emerald Grove Solar, LLC
108 MWOperating Pecos, TXERCOT Nov 20132023
Solara Solar
Solar · ConEd Development
106 MWOperating ERCOT Jul 20142016
Capricorn Ridge IV
Onshore wind · FPL Energy Capricorn Ridge Wind, LLC
105 MWOperating ERCOT Jun 2007target 2008
Limousin Oak Storage
Other · KCE TX 15, LLC
105 MWOperating Grimes, TXERCOT May 20202024
Silicon Hill Storage
Other · KCE TX 12, LLC
105 MWOperating Travis, TXERCOT Oct 20192023
Hummingbird Storage
Other · KCE TX 10, LLC
104 MWOperating Denton, TXERCOT May 20202024
Bright Arrow Storage
Other · RWE Solar Development, LLC
104 MWOperating Hopkins, TXERCOT Mar 20202023
Page 7 of 13

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)