OTHER Β· ERCOTVortex BESS
Vortex BESS is a 122 MW other request built and operating in the ERCOT interconnection queue, in Throckmorton County, Texas.
Request details
- Queue ID
- 21INR0473
- Grid region
- ERCOT (Texas)
- Developer
- AZURE SKY WIND STORAGE LLC
- Connection point (POI)
- loop 345kV 60515 Clear Crossing - 1421 WillowCr 345kV
- Location
- Throckmorton County, Texas
- Technology
- Other: 122 MW
- Total requested
- 122 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 2 December 2019
- Agreement signed
- 23 April 2021
- Proposed online date
- September 2023
- Came online
- September 2023
Location
Marker shows the centre of Throckmorton County; the queue data does not give exact sites.
Other requests in Throckmorton County
- Monarch Creek WindOnshore wind Β· 284 MW Β· agreement signed
- Sleepy Hollow BESSBattery storage Β· 123 MW Β· in study
- Ayass BESSBattery storage Β· 51.3 MW Β· in study
- Apogee Wind IIOnshore wind Β· 47.3 MW Β· in study
- Leaning Tree BESSBattery storage Β· 256 MW Β· suspended
- Lonesome Dove BESSBattery storage Β· 256 MW Β· suspended
- Vortex WindOnshore wind Β· 350 MW Β· built
- Azure Sky Wind 1Onshore wind Β· 350 MW Β· withdrawn
- Vortex Wind IIOnshore wind Β· 14.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem