🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Vortex Wind II

Vortex Wind II is a 14.0 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Throckmorton County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedJan 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0561
Grid region
ERCOT (Texas)
Location
Throckmorton County, Texas
Technology
Wind: 14.0 MW
Total requested
14.0 MW
Queue status
Withdrawn
Entered queue
2 December 2021
Withdrawn
January 2022

Location

Marker shows the centre of Throckmorton County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Throckmorton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem