United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTVortex Wind II
Vortex Wind II is a 14.0 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Throckmorton County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2021 (completed)
- Withdrawn / abandonedJan 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 22INR0561
- Grid region
- ERCOT (Texas)
- Location
- Throckmorton County, Texas
- Technology
- Wind: 14.0 MW
- Total requested
- 14.0 MW
- Queue status
- Withdrawn
- Entered queue
- 2 December 2021
- Withdrawn
- January 2022
Location
Marker shows the centre of Throckmorton County; the queue data does not give exact sites.
Other requests in Throckmorton County
- Monarch Creek WindOnshore wind · 284 MW · agreement signed
- Sleepy Hollow BESSBattery storage · 123 MW · in study
- Ayass BESSBattery storage · 51.3 MW · in study
- Apogee Wind IIOnshore wind · 47.3 MW · in study
- Leaning Tree BESSBattery storage · 256 MW · suspended
- Lonesome Dove BESSBattery storage · 256 MW · suspended
- Vortex WindOnshore wind · 350 MW · built
- Vortex BESSOther · 122 MW · built
- Azure Sky Wind 1Onshore wind · 350 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem