United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTApogee Wind II
Apogee Wind II is a 47.3 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Throckmorton County, Texas.
Queue statusIn planning
- PlanningQueued Jul 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 24INR0078
- Grid region
- ERCOT (Texas)
- Developer
- King Creek Wind Farm 3, LLC
- Connection point (POI)
- 60791 Perigee Substation 345kV
- Location
- Throckmorton County, Texas
- Technology
- Wind: 47.3 MW
- Total requested
- 47.3 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 13 July 2021
- Proposed online date
- March 2027
Location
Marker shows the centre of Throckmorton County; the queue data does not give exact sites.
Other requests in Throckmorton County
- Monarch Creek WindOnshore wind · 284 MW · agreement signed
- Sleepy Hollow BESSBattery storage · 123 MW · in study
- Ayass BESSBattery storage · 51.3 MW · in study
- Leaning Tree BESSBattery storage · 256 MW · suspended
- Lonesome Dove BESSBattery storage · 256 MW · suspended
- Vortex WindOnshore wind · 350 MW · built
- Vortex BESSOther · 122 MW · built
- Azure Sky Wind 1Onshore wind · 350 MW · withdrawn
- Vortex Wind IIOnshore wind · 14.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem