WIND + STORAGE · ERCOT

Blue Summit I Repower

Blue Summit I Repower is a 135 MW wind + storage request built and operating in the ERCOT interconnection queue, in Wilbarger County, Texas.

Queue statusOperating
  1. PlanningQueued Oct 2021 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingApr 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0550
Grid region
ERCOT (Texas)
Location
Wilbarger County, Texas
Technology
Wind: 135 MW · Battery
Total requested
135 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
31 October 2021
Came online
April 2024

Location

Marker shows the centre of Wilbarger County; the queue data does not give exact sites.