United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Wolf Ridge Windfarm

Wolf Ridge Windfarm is a 113 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Mar 2006 (completed)
  2. ConsentedNov 2007 (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
07INR0034
Grid region
ERCOT (Texas)
Developer
FPL Energy, LLC
Connection point (POI)
WHTTAIL_WR1 34.500
Technology
Wind: 113 MW
Total requested
113 MW
Study phase
IA
Queue status
Operational
Entered queue
14 March 2006
Agreement signed
1 November 2007
Proposed online date
October 2008

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem