United States βΊ Grid βΊ Interconnection queues
GAS Β· ERCOTLamar Power Upgrade
Lamar Power Upgrade is a 130 MW gas request built and operating in the ERCOT interconnection queue.
Request details
- Queue ID
- 14INR0066
- Grid region
- ERCOT (Texas)
- Developer
- Nextera
- Connection point (POI)
- Lamar Power (140067)
- Technology
- Gas: 130 MW
- Total requested
- 130 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 2 July 2013
- Agreement signed
- 22 April 2014
- Proposed online date
- June 2016
- Came online
- April 2016