SOLAR Β· ERCOT

Elara Solar

Elara Solar is a 132 MW solar request built and operating in the ERCOT interconnection queue, in Frio County, Texas.

Queue statusOperating
  1. PlanningQueued Mar 2019 (completed)
  2. ConsentedJul 2019 (completed)
  3. Construction (completed)
  4. OperatingMar 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
21INR0276
Grid region
ERCOT (Texas)
Developer
Elara Energy Project, LLC
Connection point (POI)
5866 PaloduroSw 138kV
Location
Frio County, Texas
Technology
Solar: 132 MW
Total requested
132 MW
Study phase
IA
Queue status
Operational
Entered queue
25 March 2019
Agreement signed
12 July 2019
Proposed online date
March 2022
Came online
March 2022

Location

Marker shows the centre of Frio County; the queue data does not give exact sites.