United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTDilley Solar
Dilley Solar is a 201 MW solar request in interconnection study in the ERCOT interconnection queue, in Frio County, Texas.
Queue statusIn planning
- PlanningQueued Dec 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0461
- Grid region
- ERCOT (Texas)
- Developer
- AETS Development Holdings LLC
- Connection point (POI)
- Tap 138 kV 8212 DILLEY SWITCH AEP - 8613 BIG WELLS
- Location
- Frio County, Texas
- Technology
- Solar: 201 MW
- Total requested
- 201 MW
- Study phase
- SS Started, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 23 December 2025
- Proposed online date
- June 2028
Location
Marker shows the centre of Frio County; the queue data does not give exact sites.
Other requests in Frio County
- Jukebox SolarSolar Β· 281 MW Β· in study
- Morrow Lake StorageSolar + storage Β· 201 MW Β· in study
- Hamlet Solar SLFSolar + storage Β· 201 MW Β· in study
- Hamlet Storage SLFSolar + storage Β· 201 MW Β· in study
- Bunting Solar ProjectSolar Β· 126 MW Β· in study
- Frio FarmSolar Β· 107 MW Β· in study
- Rockpile StorageBattery storage Β· 104 MW Β· in study
- Horizon SolarSolar Β· 204 MW Β· built
- Morrow Lake SolarSolar + storage Β· 201 MW Β· built
- Elara SolarSolar Β· 132 MW Β· built
- Pearsall BESSBattery storage Β· 10.0 MW Β· built
- North Leona SolarSolar Β· 205 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem