United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Rockpile Storage

Rockpile Storage is a 104 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Frio County, Texas.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
29INR0109
Grid region
ERCOT (Texas)
Developer
Rockpile Storage, LLC
Connection point (POI)
Direct to substation at 69kV Derby BUS ID #5842
Location
Frio County, Texas
Technology
Battery: 104 MW
Total requested
104 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
21 April 2025
Proposed online date
June 2029

Location

Marker shows the centre of Frio County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Frio County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem