Wigeon Whistle BESS is a 123 MW other request built and operating in the ERCOT interconnection queue, in Collin County, Texas.
Request details
- Queue ID
- 24INR0312
- Grid region
- ERCOT (Texas)
- Developer
- Wigeon Whistle BESS
- Connection point (POI)
- 811 NEVADA 138KV
- Location
- Collin County, Texas
- Technology
- Other: 123 MW
- Total requested
- 123 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 17 April 2022
- Agreement signed
- 8 December 2022
- Proposed online date
- December 2024
- Came online
- December 2024
Location
Marker shows the centre of Collin County; the queue data does not give exact sites.
Other requests in Collin County
- Drake BESSBattery storage · 257 MW · agreement signed
- Purple Sage BESS 2Battery storage · 156 MW · agreement signed
- Purple Sage BESS 1Battery storage · 156 MW · agreement signed
- Bufflehead BESSBattery storage · 153 MW · agreement signed
- Little Ridge StorageBattery storage · 252 MW · in study
- Artio Energy StorageBattery storage · 206 MW · in study
- Farmersville West BESS 2Battery storage · 9.9 MW · built
- Farmersville West BESS 1Other · 9.9 MW · built
- BRP Tigris BESSOther · 202 MW · withdrawn
- Mallard BESS IIOther · 50.4 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem