United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Farmersville West BESS 2

Farmersville West BESS 2 is a 9.9 MW battery storage request built and operating in the ERCOT interconnection queue, in Collin County, Texas.

Queue statusOperating
  1. PlanningQueued Jun 2023 (completed)
  2. ConsentedApr 2024 (completed)
  3. Construction (completed)
  4. OperatingFeb 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0618
Grid region
ERCOT (Texas)
Developer
SBESS TX 7 LLC
Connection point (POI)
Station Name: Farmersville West TNP Substation_x000D_ Station Code: FRMRSVLW_x000D_ PTI Bus#: 37291_x000D_ Load Transformer Name: FRMVW_3_x000D_ Transmission Level Voltage: 138 kV
Location
Collin County, Texas
Technology
Battery: 9.9 MW
Total requested
9.9 MW
Study phase
MRD Approved
Queue status
Operational
Entered queue
14 June 2023
Agreement signed
5 April 2024
Proposed online date
November 2024
Came online
February 2025

Location

Marker shows the centre of Collin County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Collin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem