BATTERY STORAGE · ERCOTLittle Ridge Storage
Little Ridge Storage is a 252 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Collin County, Texas.
Queue statusIn planning
- PlanningQueued May 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25INR0238
- Grid region
- ERCOT (Texas)
- Developer
- TX BESS B LLC
- Connection point (POI)
- Tap 138kV Swindell (812) - Olinger (818)
- Location
- Collin County, Texas
- Technology
- Battery: 252 MW
- Total requested
- 252 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 15 May 2023
- Proposed online date
- December 2025
Location
Marker shows the centre of Collin County; the queue data does not give exact sites.
Other requests in Collin County
- Drake BESSBattery storage · 257 MW · agreement signed
- Purple Sage BESS 2Battery storage · 156 MW · agreement signed
- Purple Sage BESS 1Battery storage · 156 MW · agreement signed
- Bufflehead BESSBattery storage · 153 MW · agreement signed
- Artio Energy StorageBattery storage · 206 MW · in study
- Wigeon Whistle BESSOther · 123 MW · built
- Farmersville West BESS 2Battery storage · 9.9 MW · built
- Farmersville West BESS 1Other · 9.9 MW · built
- BRP Tigris BESSOther · 202 MW · withdrawn
- Mallard BESS IIOther · 50.4 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem