United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Drake BESS

Drake BESS is a 257 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Collin County, Texas.

Queue statusConsented
  1. PlanningQueued Jun 2022 (completed)
  2. ConsentedMay 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0101
Grid region
ERCOT (Texas)
Developer
Mallard Energy Storage LLC
Connection point (POI)
#833 Wylie Switch 138kV
Location
Collin County, Texas
Technology
Battery: 257 MW
Total requested
257 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
2 June 2022
Agreement signed
6 May 2025
Proposed online date
July 2026

Location

Marker shows the centre of Collin County; the queue data does not give exact sites.