United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Gunsight Mt W

Gunsight Mt W is a 120 MW onshore wind request built and operating in the ERCOT interconnection queue.

Queue statusOperating
  1. PlanningQueued Jul 2006 (completed)
  2. ConsentedNov 2007 (completed)
  3. Construction (completed)
  4. OperatingSep 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
08INR0018
Grid region
ERCOT (Texas)
Developer
Invenergy
Connection point (POI)
138kV bus 1360
Technology
Wind: 120 MW
Total requested
120 MW
Study phase
IA
Queue status
Operational
Entered queue
17 July 2006
Agreement signed
12 November 2007
Proposed online date
September 2016
Came online
September 2016

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem