United States βΊ Grid βΊ Interconnection queues
ONSHORE WIND Β· ERCOTAirtricity Panther Creek 2
Airtricity Panther Creek 2 is a 115 MW onshore wind request built and operating in the ERCOT interconnection queue.
Request details
- Queue ID
- 08INR0037
- Grid region
- ERCOT (Texas)
- Developer
- Airtricity, Inc.
- Connection point (POI)
- PC__PANTHER234.500
- Technology
- Wind: 115 MW
- Total requested
- 115 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 29 November 2006
- Agreement signed
- 5 December 2007
- Proposed online date
- December 2008
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem