Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,836452.0 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,836 requests ยท page 6 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project ERAS-2025-013, Nodaway County
Gas
451 MWIn study Nodaway, MOSPP Sep 2025target 2030
Battery storage project 25-IC-1385, Hancock County
Battery storage
450 MWIn study Hancock, GASoutheast Apr 2025target 2030
Coal project ERAS-2025-009, Chouteau County
Coal
450 MWIn study Chouteau, OKSPP Oct 2025target 2026
Big Watt Power Austin-1
Gas ยท Big Watt Power Austin-1 LLC
449 MWIn study Caldwell, TXERCOT Oct 2025target 2028
Monroe ERAS
Battery storage ยท DTE Electric
432 MWIn study Monroe, MIMISO Aug 2025target 2028
Cannon Falls Uprate
Gas ยท Invenergy Cannon Falls, LLC
428 MWIn study Goodhue, MNMISO Aug 2025target 2028
Magnet Storage
Solar + storage ยท HyFuels Big Spring LLC
427 MWIn study Borden, TXERCOT Jul 2025target 2029
Gas project J4160, Ottawa County
Gas
425 MWIn study Ottawa, MIMISO Aug 2025target 2026
Battery storage project AH1-727, Loudoun County
Battery storage ยท Cardinal Energy Storage East, LLC
425 MWIn study Loudoun, VAPJM Apr 2025
Onshore wind project GEN-2024-141, Mercer County
Onshore wind
424 MWIn study Mercer, NDSPP Mar 2025target 2031
Solar + storage project GEN-2024-124, Lea County
Solar + storage
420 MWIn study Lea, NMSPP Mar 2025target 2028
Battery storage project Q2511, Maricopa County
Battery storage
419 MWIn study Maricopa, AZWest Feb 2025target 2029
Solar project J3975, Rusk County
Solar
417 MWIn study Rusk, WIMISO Mar 2025target 2030
Battery storage project PIS107, Klamath County
Battery storage
416 MWIn study Klamath, ORWest Dec 2025target 2022
Star Of Texas Solar
Solar ยท BOULEVARD ASSOCIATES, LLC
415 MWIn study Pecos, TXERCOT Aug 2025target 2029
Gas project CSUT-2025-7, El Paso County
Gas
412 MWIn study El Paso, COWest Mar 2025target 2028
Other project GEN-2025-SR9, Muskogee County
Other
410 MWIn study Muskogee, OKSPP May 2025target 2029
Wilson BESS
Battery storage ยท Dunamis BESS
410 MWIn study Wilson, TXERCOT Apr 2025target 2028
Gas project AH1-711, Wood County
Gas ยท Troy Energy, LLC
408 MWIn study Wood, OHPJM Apr 2025
18-Bravo BESS
Battery storage ยท Scout Energy Management, LLC
407 MWIn study Hunt, TXERCOT Apr 2025target 2028
Two Step Solar
Solar ยท Two Step Solar, LLC
405 MWIn study Ellis, TXERCOT Dec 2025target 2029
Merom Storage
Solar + storage ยท Hoosier Energy / Solvenz
405 MWIn study Sullivan, INMISO Dec 2025target 2028
Onshore wind project GEN-2024-102, Finney County
Onshore wind
401 MWIn study Finney, KSSPP Mar 2025target 2031
Onshore wind project GEN-2024-109, Bailey County
Onshore wind
401 MWIn study Bailey, TXSPP Mar 2025target 2031
Onshore wind project T2-057, Carbon County
Onshore wind
400 MWIn study Carbon, WYWest Sep 2025target 2029
Other project Q581, Maricopa County
Other
400 MWIn study Maricopa, AZWest May 2025target 2031
Other project SC1Q31, Sacramento County
Other
400 MWIn study Sacramento, CAWest Jul 2025target 2032
Battery storage project J4076, Jefferson Davis Parish County
Battery storage
400 MWIn study Jefferson Davis Parish, LAMISO Oct 2025target 2030
Gridline Solar
Solar ยท Big Lake Ranch LLC
400 MWIn study Crockett, TXERCOT Aug 2025target 2029
Battery storage project Q116, Clark County
Battery storage
400 MWIn study Clark, NVWest Nov 2025target 2032
Battery storage project 25-00384, Clark County
Battery storage
400 MWIn study Clark, NVWest Jul 2025target 2029
Battery storage project IA-PNM-2025-09, Valencia County
Battery storage
400 MWIn study Valencia, NMWest Mar 2025target 2029
Solar project GEN-2024-125, Elk County
Solar
400 MWIn study Elk, KSSPP Mar 2025target 2028
Battery storage project J4093, Mason County
Battery storage
400 MWIn study Mason, MIMISO Oct 2025target 2030
Solar project GEN-2024-136, Scott County
Solar
400 MWIn study Scott, KSSPP Mar 2025target 2029
Solar + storage project T2-085, Utah County
Solar + storage
400 MWIn study Utah, UTWest Sep 2025target 2030
Other project Q589, Pinal County
Other
400 MWIn study Pinal, AZWest May 2025target 2030
Onshore wind project 2025-G7
Onshore wind
400 MWIn study West Nov 2025target 2029
Battery storage project Q115, Clark County
Battery storage
400 MWIn study Clark, NVWest Nov 2025target 2032
Gas project J4110, Lafayette Parish County
Gas
400 MWIn study Lafayette Parish, LAMISO Oct 2025target 2030
Battery storage project GEN-2025-SR1, Henry County
Battery storage
400 MWIn study Henry, MOSPP Apr 2025target 2027
Gas project T2-040, Power County
Gas
400 MWIn study Power, IDWest Sep 2025target 2031
Gas project 25-00426, Storey County
Gas
400 MWIn study Storey, NVWest Jul 2025target 2028
Solar + storage project ERAS-2025-020, Lea County
Solar + storage
400 MWIn study Lea, NMSPP Oct 2025target 2030
Battery storage project LGE-CS2025-001, Jefferson County
Battery storage
400 MWIn study Jefferson, KYSoutheast Nov 2025target 2029
Exergy Energy West Texas Natural Gas Reciprocating Power I
Gas ยท August Partners LLC
400 MWIn study Reeves, TXERCOT Jul 2025target 2027
Battery storage project J3992, Eaton County
Battery storage
400 MWIn study Eaton, MIMISO Apr 2025target 2028
Springfield Solar
Solar ยท BOULEVARD ASSOCIATES, LLC
400 MWIn study Pecos, TXERCOT Sep 2025target 2028
Battery storage project 25-00386, Storey County
Battery storage
400 MWIn study Storey, NVWest Jul 2025target 2031
Onshore wind project GEN-2024-221, Roosevelt County
Onshore wind
400 MWIn study Roosevelt, NMSPP Mar 2025target 2030

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)