United States › Grid › Interconnection queues › Louisiana
GAS · MISOGas project J4110, Lafayette Parish County
Gas project J4110, Lafayette Parish County is a 400 MW gas request in interconnection study in the MISO interconnection queue, in Lafayette Parish County, Louisiana, connecting to CLECO POWER.
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4110
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- CLECO POWER
- Connection point (POI)
- Rork - Sellers Road 230.0kV
- Location
- Lafayette Parish County, Louisiana
- Technology
- Gas: 400 MW
- Total requested
- 400 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 7 October 2025
- Proposed online date
- June 2030
Location
Marker shows the centre of Lafayette Parish County; the queue data does not give exact sites.
Other requests in Lafayette Parish County
- Solar project J1818, Lafayette Parish CountySolar · 80.0 MW · agreement signed
- Battery storage project J4098, Lafayette Parish CountyBattery storage · 300 MW · in study
- Gas project J2791, Lafayette Parish CountyGas · 263 MW · in study
- Solar project J2888, Lafayette Parish CountySolar · 500 MW · withdrawn
- Solar project J645, Lafayette Parish CountySolar · 48.8 MW · withdrawn
- Solar project J710, Lafayette Parish CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem