🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Louisiana

SOLAR · MISO

Solar project J1818, Lafayette Parish County

Solar project J1818, Lafayette Parish County is a 80.0 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Lafayette Parish County, Louisiana, connecting to LAFAYETTE UTILITIES SYSTEM.

Queue statusConsented
  1. PlanningQueued Jun 2020 (completed)
  2. ConsentedJan 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1818
Grid region
MISO (Midcontinent)
Utility / transmission owner
LAFAYETTE UTILITIES SYSTEM
Connection point (POI)
Northeast (Moss) 69kV
Location
Lafayette Parish County, Louisiana
Technology
Solar: 80.0 MW
Total requested
80.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
19 June 2020
Agreement signed
18 January 2023
Proposed online date
June 2026

Location

Marker shows the centre of Lafayette Parish County; the queue data does not give exact sites.

Power plants in Louisiana · Transmission lines in Louisiana

Other requests in Lafayette Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem