United States › Grid › Interconnection queues › Kentucky
BATTERY STORAGE · SOUTHEASTBattery storage project LGE-CS2025-001, Jefferson County
Battery storage project LGE-CS2025-001, Jefferson County is a 400 MW battery storage request in interconnection study in the Southeast interconnection queue, in Jefferson County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
- PlanningQueued Nov 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- LGE-CS2025-001
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- Cane Run CT Substation, 138 kV
- Location
- Jefferson County, Kentucky
- Technology
- Battery: 400 MW
- Total requested
- 400 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 18 November 2025
- Proposed online date
- February 2029
Location
Marker shows the centre of Jefferson County; the queue data does not give exact sites.
Other requests in Jefferson County
- Gas project LGE-GIS-2013-001, Jefferson CountyGas · 691 MW · agreement signed
- Gas project LGE-GIS-2010-001, Jefferson CountyGas · 690 MW · agreement signed
- Gas project LGE-GIS-2022-003, Jefferson CountyGas · 660 MW · agreement signed
- Gas project LGE-GIS-2024-006, Jefferson CountyGas · 94.0 MW · agreement signed
- Hydro project LGE-GIS-2011-003, Jefferson CountyHydro · 21.0 MW · agreement signed
- Gas project LGE-CS2025-002, Jefferson CountyGas · 680 MW · in study
- Gas project LGE-GIS-2010-002, Jefferson CountyGas · 704 MW · withdrawn
- Gas project LGE-GIS-2021-005, Jefferson CountyGas · 635 MW · withdrawn
- Battery storage project LGE-GIS-2021-011, Jefferson CountyBattery storage · 300 MW · withdrawn
- Battery storage project LGE-GIS-2021-016, Jefferson CountyBattery storage · 250 MW · withdrawn
- Gas project LGE-GIS-2011-002, Jefferson CountyGas · 30.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem