United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
GAS Β· SOUTHEASTGas project LGE-GIS-2021-005, Jefferson County
Gas project LGE-GIS-2021-005, Jefferson County is a 635 MW gas request withdrawn in the Southeast interconnection queue, in Jefferson County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2021 (completed)
- Withdrawn / abandonedOct 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- LGE-GIS-2021-005
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- Mill Creek 345 kV Station
- Location
- Jefferson County, Kentucky
- Technology
- Gas: 635 MW
- Total requested
- 635 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 21 January 2021
- Proposed online date
- December 2025
- Withdrawn
- October 2021
Location
Marker shows the centre of Jefferson County; the queue data does not give exact sites.
Other requests in Jefferson County
- Gas project LGE-GIS-2013-001, Jefferson CountyGas Β· 691 MW Β· agreement signed
- Gas project LGE-GIS-2010-001, Jefferson CountyGas Β· 690 MW Β· agreement signed
- Gas project LGE-GIS-2022-003, Jefferson CountyGas Β· 660 MW Β· agreement signed
- Gas project LGE-GIS-2024-006, Jefferson CountyGas Β· 94.0 MW Β· agreement signed
- Hydro project LGE-GIS-2011-003, Jefferson CountyHydro Β· 21.0 MW Β· agreement signed
- Gas project LGE-CS2025-002, Jefferson CountyGas Β· 680 MW Β· in study
- Battery storage project LGE-CS2025-001, Jefferson CountyBattery storage Β· 400 MW Β· in study
- Gas project LGE-GIS-2010-002, Jefferson CountyGas Β· 704 MW Β· withdrawn
- Battery storage project LGE-GIS-2021-011, Jefferson CountyBattery storage Β· 300 MW Β· withdrawn
- Battery storage project LGE-GIS-2021-016, Jefferson CountyBattery storage Β· 250 MW Β· withdrawn
- Gas project LGE-GIS-2011-002, Jefferson CountyGas Β· 30.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem