United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Other interconnection queue in the USA — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown32874.4 GW
Active in queue74.4 GW328 requests
Agreement signed5,506 MW27 requests
Withdrawn1,273328.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

328 requests · page 5 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Surplus; J728
Other
90.0 MWIn study Isabella, MIMISO Aug 2022target 2025
Surplus; J717
Other
90.0 MWIn study Isabella, MIMISO Aug 2022target 2025
Surplus; J1224/J1329
Other
85.1 MWIn study Washtenaw, MIMISO Oct 2024target 2028
Other project G0877, Lane County
Other
80.0 MWIn study Lane, ORWest Jun 2023target 2029
Other project G0883, Lane County
Other
80.0 MWIn study Lane, ORWest Jun 2023target 2029
Other project PP00043, Jones County
Other
80.0 MWIn study Jones, NCSoutheast Aug 2025target 2029
Other project G0885, Linn County
Other
80.0 MWIn study Linn, ORWest Jun 2023target 2029
Surplus; Old Gold
Other
80.0 MWIn study Worth, IAMISO Jun 2024target 2029
Other project PP00035, Wilson County
Other
80.0 MWIn study Wilson, NCSoutheast Jun 2025target 2029
Other project PP00051, Duplin County
Other
80.0 MWIn study Duplin, NCSoutheast Aug 2025target 2029
Other project PP00042, Granville County
Other
80.0 MWIn study Granville, NCSoutheast Jun 2025target 2027
Surplus; Pine River Solar
Other
80.0 MWAgreement signed Gratiot, MIMISO Apr 2022target 2023
Other project GI-2020-139, Riverside County
Other
80.0 MWIn study Riverside, CAWest Nov 2020target 2027
Other project 72, Pima County
Other
80.0 MWIn study Pima, AZWest Jan 2020target 2022
Other project PP00044, Duplin County
Other
80.0 MWIn study Duplin, NCSoutheast Aug 2025target 2029
Other project Q559, Maricopa County
Other
80.0 MWIn study Maricopa, AZWest May 2024target 2028
Other project Q557, Navajo County
Other
75.0 MWIn study Navajo, AZWest May 2024target 2026
Surplus; J986
Other
75.0 MWIn study MISO Apr 2022target 2022
Other project PP00057, Marlboro County
Other
74.9 MWIn study Marlboro, SCSoutheast Nov 2025target 2028
Other project PP00056, Marion County
Other
74.9 MWIn study Marion, SCSoutheast Oct 2025target 2027
Other project PP00055, Marlboro County
Other
74.9 MWIn study Marlboro, SCSoutheast Oct 2025target 2027
Other project 66, Stevens County
Other
71.0 MWAgreement signed Stevens, WAWest Jul 2018target 2026
Other project Q66, Stevens County
Other
71.0 MWAgreement signed Stevens, WAWest target 2026
Altamaha Green Energy
Other
70.0 MWIn study Wayne, GASoutheast Aug 2024target 2028
Other project PP00036, Robeson County
Other
70.0 MWIn study Robeson, NCSoutheast Jul 2025target 2028
Other project PP00045, Lenoir County
Other
70.0 MWIn study Lenoir, NCSoutheast Aug 2025target 2029
Other project PP00037, Wayne County
Other
67.0 MWIn study Wayne, NCSoutheast Jul 2025target 2029
Other project GEN-2024-231, Richardson County
Other
65.0 MWIn study Richardson, NESPP Mar 2025target 2029
Other project PP00050, Cumberland County
Other
65.0 MWIn study Cumberland, NCSoutheast Sep 2025target 2029
Other project PP00029, Marion County
Other
63.9 MWIn study Marion, SCSoutheast Jun 2025target 2027
Surplus; J878
Other
60.0 MWIn study MISO Apr 20212024
Surplus; J1067
Other
60.0 MWIn study White, INMISO May 20222024
HIP ESS Project
Other
60.0 MWPaused / redesign Leon, TXERCOT
Bottle Rock Power
Other
56.9 MWAgreement signed Lake, CACAISO Sep 20052007
Surplus; J928
Other
55.0 MWIn study Delta, MIMISO Apr 2022target 2025
Other project Q608, Pinal County
Other
55.0 MWIn study Pinal, AZWest May 2025target 2028
Tokyo TxHSR TPSS EW-1
Other · Texas Central Rail Holdings, LLC
50.0 MWIn study Ellis, TXERCOT Jan 2019target 2028
Surplus; J1369
Other
50.0 MWAgreement signed Dubois, INMISO May 2022target 2022
Surplus; J1369
Other
50.0 MWIn study Dubois, INMISO Apr 2023target 2024
Surplus; J1002
Other
50.0 MWIn study Waushara, WIMISO May 2022target 2023
Surplus; G905
Other
50.0 MWIn study Midland, MIMISO Aug 2024target 2026
Other project PP00038, Nash County
Other
50.0 MWIn study Nash, NCSoutheast Jul 2025target 2029
Atlanta TxHSR TPSS DS-1
Other · Texas Central Rail Holdings, LLC
50.0 MWIn study Dallas, TXERCOT Jan 2019target 2028
Other project Q592, Maricopa County
Other
50.0 MWIn study Maricopa, AZWest May 2025target 2031
Surplus; J1386
Other
50.0 MWIn study Lake, INMISO May 2022target 2028
Barcelona TxHSR TPSS HN-4
Other · Texas Central Rail Holdings, LLC
50.0 MWIn study Harris, TXERCOT Jan 2019target 2028
Other project GEN-2025-SR18, Jackson County
Other
50.0 MWIn study Jackson, MOSPP Jun 2025target 2029
Surplus; J1386
Other
50.0 MWIn study Lake, INMISO Apr 2023target 2024
Surplus; Gratiot Solar
Other
50.0 MWIn study MISO Apr 2022target 2023
Mea Nug
Other
50.0 MWAgreement signed Monongalia, WVPJM Sep 2020target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)