United States › Grid › Interconnection queues › Washington
OTHER · WESTOther project Q66, Stevens County
Other project Q66, Stevens County is a 71.0 MW other request with a signed interconnection agreement in the West interconnection queue, in Stevens County, Washington, connecting to Avista Utilities.
Queue statusConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- Q66
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Avista Utilities
- Connection point (POI)
- Kettle Falls 115kV Station
- Location
- Stevens County, Washington
- Technology
- Other: 71.0 MW
- Total requested
- 71.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- LGIA
- Queue status
- Active
- Proposed online date
- June 2026
Location
Marker shows the centre of Stevens County; the queue data does not give exact sites.
Power plants in Washington · Transmission lines in Washington
Other requests in Stevens County
- Other project 66, Stevens CountyOther · 71.0 MW · agreement signed
- Solar + storage project 84, Stevens CountySolar + storage · 5.0 MW · in study
- Other project hist_q71, Stevens CountyOther · 4.5 MW · suspended
- Solar project TCS-12, Stevens CountySolar · 5.0 MW · withdrawn
- Solar project 105, Stevens CountySolar · 5.0 MW · withdrawn
- Solar + storage project Q84, Stevens CountySolar + storage · 5.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem