United States βΊ Grid βΊ Interconnection queues βΊ Washington
SOLAR Β· WESTSolar project TCS-12, Stevens County
Solar project TCS-12, Stevens County is a 5.0 MW solar request withdrawn in the West interconnection queue, in Stevens County, Washington, connecting to Avista Utilities.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedAug 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- TCS-12
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Avista Utilities
- Connection point (POI)
- 13.2kv Distribution on the Orin Rice Rd
- Location
- Stevens County, Washington
- Technology
- Solar: 5.0 MW
- Total requested
- 5.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Request Status: Withdrawn; Facilities Study: N/A; Phase One Cluster Study: N/A; Phase One Re-Study: N/A; Phase Two Clust
- Queue status
- Withdrawn
- Entered queue
- 3 March 2020
- Proposed online date
- June 2021
- Withdrawn
- August 2022
Location
Marker shows the centre of Stevens County; the queue data does not give exact sites.
Power plants in Washington Β· Transmission lines in Washington
Other requests in Stevens County
- Other project 66, Stevens CountyOther Β· 71.0 MW Β· agreement signed
- Other project Q66, Stevens CountyOther Β· 71.0 MW Β· agreement signed
- Solar + storage project 84, Stevens CountySolar + storage Β· 5.0 MW Β· in study
- Other project hist_q71, Stevens CountyOther Β· 4.5 MW Β· suspended
- Solar project 105, Stevens CountySolar Β· 5.0 MW Β· withdrawn
- Solar + storage project Q84, Stevens CountySolar + storage Β· 5.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem