United States › Grid › Interconnection queues › Texas

OTHER · ERCOT

Barcelona TxHSR TPSS HN-4

Barcelona TxHSR TPSS HN-4 is a 50.0 MW other request in interconnection study in the ERCOT interconnection queue, in Harris County, Texas.

Queue statusIn planning
  1. PlanningQueued Jan 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0002
Grid region
ERCOT (Texas)
Developer
Texas Central Rail Holdings, LLC
Connection point (POI)
tap 138kV 45885 HocklyC - 46220 Peters
Location
Harris County, Texas
Technology
Other: 50.0 MW
Total requested
50.0 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
30 January 2019
Proposed online date
July 2028

Location

Marker shows the centre of Harris County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Harris County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem