United States › Grid › Interconnection queues › Georgia
OTHER · SOUTHEASTAltamaha Green Energy
Altamaha Green Energy is a 70.0 MW other request in interconnection study in the Southeast interconnection queue, in Wayne County, Georgia, connecting to Georgia Transmission.
Queue statusIn planning
- PlanningQueued Aug 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GI-195
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Georgia Transmission
- Connection point (POI)
- Jessup – Ludowici Primary 115 kV TL
- Location
- Wayne County, Georgia
- Technology
- Other: 70.0 MW
- Total requested
- 70.0 MW
- Study phase
- Facilities Study
- Queue status
- Active
- Entered queue
- 20 August 2024
- Proposed online date
- March 2028
Location
Marker shows the centre of Wayne County; the queue data does not give exact sites.
Other requests in Wayne County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem