United States βΊ Grid βΊ Interconnection queues βΊ Georgia
SOLAR Β· SOUTHEASTSolar project IC-321, Wayne County
Solar project IC-321, Wayne County is a 50.0 MW solar request withdrawn in the Southeast interconnection queue, in Wayne County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2013 (completed)
- Withdrawn / abandonedMay 2014 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-321
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Jesup - West Brunswick 115 kV Line
- Location
- Wayne County, Georgia
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 29 October 2013
- Withdrawn
- May 2014
Location
Marker shows the centre of Wayne County; the queue data does not give exact sites.
Other requests in Wayne County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem