🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Ohio

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Ohio — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown18519.7 GW
Active in queue19.7 GW185 requests
Agreement signed8,251 MW65 requests
Withdrawn59480.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

185 requests · page 4 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project AH2-093, Greene County
Solar + storage
32.0 MWIn study Greene, OHPJM Jan 2022target 2025
Gas project AH1-706, Trumbull County
Gas · Clean Energy Future - Lordstown, LLC
30.5 MWIn study Trumbull, OHPJM Apr 2025
Solar + storage project AH2-409, Wood County
Solar + storage
30.1 MWIn study Wood, OHPJM Mar 2022target 2025
Solar project AI2-337, Madison County
Solar
30.0 MWIn study Madison, OHPJM Mar 2023target 2023
Scioto Solar
Solar
30.0 MWAgreement signed Hardin, OHPJM Mar 2019target 2026
Solar project AI2-427, Licking County
Solar
26.4 MWIn study Licking, OHPJM Mar 2023target 2027
Blue Creek Wind Farm
Solar
26.0 MWPaused / redesign Van Wert, OHPJM Sep 2018target 2024
Gas project AH1-719, Washington County
Gas · Washington Power Generation LLC
24.0 MWIn study Washington, OHPJM Apr 2025
Gas project AH1-686, Lawrence County
Gas · Hanging Rock Power Company LLC
24.0 MWIn study Lawrence, OHPJM Apr 2025
Gas project AH1-704, Monroe County
Gas · Long Ridge Energy Generation LLC
24.0 MWIn study Monroe, OHPJM Apr 2025
Solar project AI2-341, Marion County
Solar
22.8 MWIn study Marion, OHPJM Mar 2023target 2024
Solar project AH1-059, Knox County
Solar · Frasier Solar, LLC
21.0 MWIn study Knox, OHPJM Mar 2025target 2024
Solar project AH2-160, Highland County
Solar
20.0 MWIn study Highland, OHPJM Mar 2022target 2025
Eaton OH Solar
Solar
20.0 MWAgreement signed Preble, OHPJM Feb 2017target 2027
Gas project AH2-111, Monroe County
Gas
20.0 MWIn study Monroe, OHPJM Feb 2022target 2022
Blue Creek Wind Farm
Solar
20.0 MWPaused / redesign Van Wert, OHPJM Feb 2017target 2024
Solar project AI2-346, Harrison County
Solar
20.0 MWIn study Harrison, OHPJM Mar 2023target 2025
Crossroads Solar I
Solar · Crossroads Solar I, LLC
20.0 MWIn study Morrow, OHPJM Apr 2025target 2024
Solar project AH2-028A, Pickaway County
Solar
20.0 MWIn study Pickaway, OHPJM Nov 2021target 2025
Solar + storage project AI1-175, Marion County
Solar + storage
19.5 MWIn study Marion, OHPJM Sep 2022target 2024
Solar project AI2-397, Preble County
Solar
19.2 MWIn study Preble, OHPJM Mar 2023target 2026
Angelina Solar I
Solar
18.0 MWAgreement signed Preble, OHPJM Aug 2019target 2028
Solar project AI2-348, Clermont County
Solar
17.4 MWIn study Clermont, OHPJM Mar 2023target 2025
Solar project AI1-139, Lorain County
Solar
14.8 MWIn study Lorain, OHPJM Sep 2022target 2025
Other project AH2-006, Pickaway County
Other
14.2 MWIn study Pickaway, OHPJM Oct 2021target 2024
Battery storage project AI2-483, Licking County
Battery storage
13.4 MWIn study Licking, OHPJM Mar 2023target 2025
Juliet Energy
Solar · Juliet Energy Project, LLC
12.0 MWAgreement signed Wood, OHPJM Feb 2020target 2027
West Lorain 138 kV Power Plant
Gas
11.3 MWAgreement signed Lorain, OHPJM Sep 2020target 2028
Other project AH2-007, Fayette County
Other
10.1 MWIn study Fayette, OHPJM Oct 2021target 2024
Other project AH1-661, Muskingum County
Other · Tallgrass Muskingum Community Power, LLC
10.1 MWIn study Muskingum, OHPJM Feb 2025target 2023
Solar project AG2-057, Morrow County
Solar · Crossroads Solar I, LLC
10.0 MWIn study Morrow, OHPJM Apr 2025target 2022
Solar project AI2-398, Preble County
Solar
9.6 MWIn study Preble, OHPJM Mar 2023target 2026
West Lorain 138 kV Power Plant
Gas
8.0 MWAgreement signed Lorain, OHPJM Oct 2019target 2028
Other project L008, Delaware County
Other
-4.0 MWIn study Delaware, OHMISO Nov 2004target 2004
Other project L004, Williams County
Other
-22.0 MWIn study Williams, OHMISO Jul 2004target 2009
Page 4 of 4

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)