Blue Creek Wind Farm

Blue Creek Wind Farm is a 20.0 MW solar request suspended in the PJM interconnection queue, in Van Wert County, Ohio, connecting to AEP.

Queue statusPaused / redesign
  1. PlanningQueued Feb 2017 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AC2-044
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Maddox Creek 345kV
Location
Van Wert County, Ohio
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
7 February 2017
Proposed online date
November 2024

Location

Marker shows the centre of Van Wert County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Van Wert County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem