SOLAR · PJM

Solar project AH2-264, Van Wert County

Solar project AH2-264, Van Wert County is a 115 MW solar request in interconnection study in the PJM interconnection queue, in Van Wert County, Ohio, connecting to AEP.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AH2-264
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Logtown - North Delphos 138 kV
Location
Van Wert County, Ohio
Technology
Solar: 115 MW
Total requested
115 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
9 March 2022
Proposed online date
March 2026

Location

Marker shows the centre of Van Wert County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Van Wert County