United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Southeast (non-ISO utilities) — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,067161.4 GW
Active in queue161.4 GW1,067 requests
Agreement signed37.8 GW192 requests
Withdrawn2,738603.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,067 requests · page 4 of 22
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 25-IC-1320A, Lee County
Gas
240 MWIn study Lee, ALSoutheast Apr 2025target 2029
Gas project 588, Shelby County
Gas
238 MWIn study Shelby, TNSoutheast Nov 2023target 2024
Onshore wind project GI-53, Nodaway County
Onshore wind
238 MWAgreement signed Nodaway, MOSoutheast May 2016target 2018
Onshore wind project GI-61, Nodaway County
Onshore wind
230 MWAgreement signed Nodaway, MOSoutheast May 2017target 2019
Solar project IC-1014, Jeff Davis County
Solar
230 MWPaused / redesign Jeff Davis, GASoutheast Jan 2022target 2025
Gas project 25-IC-1317, Autauga County
Gas
229 MWIn study Autauga, ALSoutheast Apr 2025target 2029
Solar project IC-1206, Laurens County
Solar
225 MWAgreement signed Laurens, GASoutheast Nov 2023target 2028
Malta Project
Battery storage
225 MWIn study Brevard, FLSoutheast Mar 2023target 2026
Solar project IC-1098, Taylor County
Solar
225 MWPaused / redesign Taylor, GASoutheast Nov 2022target 2027
Battery storage project 587, Hawkins County
Battery storage
225 MWIn study Hawkins, TNSoutheast Oct 2023target 2029
Battery storage project 292, Pinellas County
Battery storage · Duke Energy Florida, LLC
225 MWUnder construction Pinellas, FLSoutheast Apr 2021target 2025
Hammond Solar
Solar
225 MWIn study Floyd, GASoutheast Sep 2023target 2025
Solar project IC-908, Turner County
Solar
220 MWPaused / redesign Turner, GASoutheast Oct 2020target 2023
Battery storage project IC-1187, Wilkinson County
Battery storage
220 MWAgreement signed Wilkinson, GASoutheast Oct 2023target 2027
Gas project 200, Anderson County
Gas
209 MWIn study Anderson, SCSoutheast Jun 2023
Pecan Energy Storage
Solar + storage
208 MWIn study Mitchell, GASoutheast Oct 2023target 2029
Gas project 303, Colleton County
Gas
208 MWIn study Colleton, SCSoutheast May 2025target 2032
Gas project 302, Colleton County
Gas
208 MWIn study Colleton, SCSoutheast May 2025target 2032
Washington County Solar
Solar + storage
203 MWIn study Washington, GASoutheast Oct 2024target 2027
Solar project 957146, Newberry County
Solar
200 MWIn study Newberry, SCSoutheast Jun 2024
Pepper Hammock Solar
Solar
200 MWIn study Glynn, GASoutheast Jun 2022target 2024
Solar project 512, Lee County
Solar
200 MWIn study Lee, MSSoutheast Aug 2022target 2028
Solar project IC-1266, Bullock County
Solar
200 MWAgreement signed Bullock, ALSoutheast Mar 2024target 2027
Solar project IC-800, Taylor County
Solar
200 MWAgreement signed Taylor, GASoutheast Jul 2019target 2023
Solar project IC-990, Toombs County
Solar
200 MWPaused / redesign Toombs, GASoutheast Oct 2021target 2025
Solar + storage project IC-1013, Oglethorpe County
Solar + storage
200 MWPaused / redesign Oglethorpe, GASoutheast Jan 2022target 2025
Solar project IC-1113, Lamar County
Solar
200 MWPaused / redesign Lamar, MSSoutheast Jan 2023target 2027
Solar project 445, Moore County
Solar
200 MWAgreement signed Moore, TNSoutheast Jun 2020target 2025
Solar project 423, Clay County
Solar
200 MWAgreement signed Clay, MSSoutheast Apr 2020target 2026
Battery storage project 600, Clay County
Battery storage
200 MWIn study Clay, MSSoutheast Dec 2023target 2026
Battery storage project IC-1272, Paulding County
Battery storage
200 MWIn study Paulding, GASoutheast Mar 2024target 2030
Solar + storage project IC-839, Sumter County
Solar + storage
200 MWAgreement signed Sumter, GASoutheast Nov 2019target 2027
Fairboro Solar
Solar
200 MWIn study Ware, GASoutheast Dec 2021target 2023
Solar + storage project LGE-GIS-2021-009, Hardin County
Solar + storage
200 MWPaused / redesign Hardin, KYSoutheast Mar 2021target 2026
Solar project IC-1195, Warren County
Solar
200 MWAgreement signed Warren, GASoutheast Oct 2023target 2028
Solar project IC-1204, Jefferson County
Solar
200 MWAgreement signed Jefferson, GASoutheast Nov 2023target 2028
Solar project IC-1180, Jones County
Solar
200 MWPaused / redesign Jones, MSSoutheast Oct 2023target 2028
Solar project 385, Lawrence County
Solar
200 MWAgreement signed Lawrence, ALSoutheast Aug 2019target 2026
SR Bartown frmly Jefferson
Solar
200 MWIn study Jefferson, GASoutheast Dec 2024target 2029
Battery storage project 661, Shelby County
Battery storage
200 MWIn study Shelby, TNSoutheast Oct 2024target 2026
Live Oak Solar
Solar + storage
200 MWIn study Laurens, GASoutheast May 2023target 2026
Union City Storage I
Battery storage
200 MWIn study Fulton, GASoutheast Dec 20192022
Solar + storage project 25-IC-1379, Butler County
Solar + storage
200 MWIn study Butler, ALSoutheast Apr 2025target 2028
Battery storage project 25RSC-004, Marshall County
Battery storage
200 MWIn study Marshall, KYSoutheast Jul 2025target 2030
Solar project 191, Sumter County
Solar
200 MWIn study Sumter, SCSoutheast Jun 2023target 2027
Solar project 25-IC-1368, Mobile County
Solar
200 MWIn study Mobile, ALSoutheast Apr 2025target 2029
Solar project IC-1088, Lee County
Solar
200 MWAgreement signed Lee, GASoutheast Nov 2022target 2027
Solar project IC-1097, Emanuel County
Solar
200 MWAgreement signed Emanuel, GASoutheast Nov 2022target 2028
Solar project IC-1094, Irwin County
Solar
200 MWAgreement signed Irwin, GASoutheast Nov 2022target 2028
Solar + storage project IC-1042, Rockdale County
Solar + storage
200 MWPaused / redesign Rockdale, GASoutheast Jul 2022target 2026
Page 4 of 22

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)