SR Bartown frmly Jefferson

SR Bartown frmly Jefferson is a 200 MW solar request in interconnection study in the Southeast interconnection queue, in Jefferson County, Georgia, connecting to Georgia Transmission.

Queue statusIn planning
  1. PlanningQueued Dec 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-204
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Georgia Transmission
Connection point (POI)
Sandersville #1 - Wadley 115 kV via Pervis Road -Louisville Junction 115 kV tap
Location
Jefferson County, Georgia
Technology
Solar: 200 MW
Total requested
200 MW
Study phase
System Impact Study
Queue status
Active
Entered queue
18 December 2024
Proposed online date
December 2029

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.

Power plants in Georgia · Transmission lines in Georgia

Other requests in Jefferson County