United States › Grid › Interconnection queues › South Carolina
SOLAR · SOUTHEASTSolar project 191, Sumter County
Solar project 191, Sumter County is a 200 MW solar request in interconnection study in the Southeast interconnection queue, in Sumter County, South Carolina, connecting to Santee Cooper.
- PlanningQueued Jun 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 191
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Santee Cooper
- Location
- Sumter County, South Carolina
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- 2023 Cluster
- Queue status
- Active
- Entered queue
- 1 June 2023
- Proposed online date
- January 2027
Location
Marker shows the centre of Sumter County; the queue data does not give exact sites.
Power plants in South Carolina · Transmission lines in South Carolina
Other requests in Sumter County
- Solar project 15918, Sumter CountySolar · 100 MW · withdrawn
- Solar project 5224, Sumter CountySolar · 100 MW · withdrawn
- Solar project 39370, Sumter CountySolar · 100 MW · withdrawn
- Solar + storage project 204, Sumter CountySolar + storage · 75.0 MW · withdrawn
- Solar project 920655, Sumter CountySolar · 75.0 MW · withdrawn
- Solar project 128, Sumter CountySolar · 74.9 MW · withdrawn
- Solar project 911187, Sumter CountySolar · 74.9 MW · withdrawn
- Battery storage project 221, Sumter CountyBattery storage · 50.0 MW · withdrawn
- Solar + storage project 163, Sumter CountySolar + storage · 50.0 MW · withdrawn
- Solar project 276, Sumter CountySolar · 49.9 MW · withdrawn
- Solar project 918717, Sumter CountySolar · 40.0 MW · withdrawn
- Solar project 103, Sumter CountySolar · 7.4 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem